NW 136th Avenue Lane Closures Near State Road 84 and the I-595 Interchange

The Florida Department of Transportation (FDOT) has begun an intersection improvements project on NW 136th Avenue and State Road 84 (pictured in the map to the right extending from the I-595 Interchange north and including the bridge running over the North New River Canal) that will result in road construction through Fall 2020.

Beginning the week of July 8th and continuing through Spring 2020, FDOT will close the Southbound bridge and re-route Southbound traffic into the two rightmost lanes on the current Northbound bridge. During this period, traffic will remain reduced to 2 lanes in each direction. While full road closures will be minimized, there may be single lane closures during non-peak hours (Sunday through Thursday between 10 p.m. and 6 a.m.)

The construction will result in widened bridges with an additional lane on each side, designated bike lanes, new LED road lighting, and a designated right-turn lane from westbound SR 84 to northbound NW 136th Avenue. For extended details of each phase of the project, please see the summary below.
  • Phase I Improvements
    • Remove the existing traffic separator along
      NW 136 Avenue within the project limits
    • Relocate City of Sunrise’s existing force main
    • Shift all traffic lanes on NW 136 Avenue at SR 84 east
  • Phase II Improvements
    • Pedestrians will be detoured to the east side of the
      road during this phase
    • Remove and replace the New North River Canal
      southbound bridge
    • Widen southbound NW 136 Avenue for the new curb
      and gutter and sidewalk
  • Phase III Improvements
    • Pedestrians will be detoured to the west side during this phase
    • Shift all traffic lanes on NW 136 Avenue west to the newly
      constructed southbound bridge
    • Remove and replace the New North River Canal northbound bridge
    • Widen northbound NW 136 Avenue for the new curb and gutter
      sidewalk
    • Widen westbound SR 84 to accommodate a second dedicated
      right-turn lane
    • Construct the new barrier wall on westbound SR 84
    • Install a new overhead sign structure on westbound SR 84
  • Phase IV Improvements
    • Construct a new traffic separator underneath the I-595 overpass
  • Phase V Improvements
    • Mill and resurface the project limits

Have a question about this project? Contact 
FDOT's designated community outreach specialist Rebecca Guerrero at rguerrero@corradino.com.
 